Construction process of a duplex penthouse in Sathorn Gardens Bangkok. Designed and construction management by regroup architecture.
03. November 2020 – Living room 2nd floor
02. November 2020 – Entrance hall stone floor polishing
30. October 2020 – Kitchen installation
28. October 2020 – Interior finishing – Wallpaper living room
28. October 2020 – Interior finishing – Bathroom
26. October 2020 – Interior finishing – Staircase
22. October 2020 – Build in wine cellar and book shelf
21. October 2020 – Build in Closets
13. – 22. October 2020 – Stone floor entrance hall
15. October 2020 – Counter master bathroom
09. October 2020 – Spiderman window and facade repair
06. October 2020 – Wall and door finishes
01. October 2020 – Staircase marble floor installation
24. September 2020 – Rooftop deck and pool
21. September 2020 – carpenter, tiles, and light
10. September 2020 – Big Slab tiles installation on floor 2
08. September 2020 – Pool and wine cellar tile work under progress
27. August 2020 – Indoor ceiling work almost finished
15. August 2020 – Outdoor pool on terrace 41th floor
13. August 2020 – Ceiling work started
1. August 2020 – Ceramic tiles in Bathrooms
22. July 2020 – Bathroom tile work start
20. July 2020 – Pool and terrace
07. July 2020 – Built -in start
18. June 2020 – Staircase
02. June 2020 – AC system installation
30. April 2020 – Staircase
19. April 2020 – Entrance hall
16. April 2020 – 1st floor
10. April 2020 – 2nd floor
27. March 2020 – Terrace
25. March 2020 – Construction start inner walls
17. March 2020 – Construction start