regroup designed the new 500sqm office complex for Transpo International based on nine shipping containers, located in a warehouse.

CONSTRUCTION Journal

15th September 2018 

Installation of inner walls and ceilings are almost done. Main staircase is fabricated between the 1st and 2nd shipping container units. LAN cable and light installation started… one more week to go!

73_transpo-installation_21

73_transpo-installation_23

73_transpo-installation_24

73_transpo-installation_25

73_transpo-installation_28

73_transpo-installation_29

73_transpo-installation_26

73_transpo-installation_27

 

30th September 2018 

Installation of floor and wall construction between the shipping containers. The office-space get’s shaped… finished in 3 weeks.

73_transpo-installation_09

73_transpo-installation_10

73_transpo-installation_11

73_transpo-installation_12

73_transpo-installation_13

73_transpo-installation_14

73_transpo-installation_15

73_transpo-installation_16

3rd September 2018 

73_transpo-installation_01

73_transpo-installation_02

73_transpo-installation_03b

73_transpo-installation_04

73_transpo-installation_05

73_transpo-installation_06

73_transpo-installation_07

73_transpo-installation_08

 

30th August 2018 

73_transpo-metalwork_06

73_transpo-metalwork_07

73_transpo-metalwork_08

73_transpo-metalwork_09

15th August 2018 

73_transpo-metalwork_01

73_transpo-metalwork_02

73_transpo-metalwork_03

73_transpo-metalwork_04

73_transpo-metalwork_05

 

Workscope:

  • Project design, interior design
  • Construction planning
  • Quality survey construction site

 

Location Bangkok Rangsit
size 500 sqm on 2 floors
containres 8×40″, 1x 20″
workplaces 80
construction Q3 2018