Construction process of the new Swiss Chamber of Commerce office pavilion on the Swiss embassy Bangkok.
Construction process: Off site pre fabrication
14.06.21: Sourcing of 40″ HC shipping container
21.06.21: Splitting 40″ container to two 20″ HC modules
29.06.21: Metal fabrication
08.07.21: Metal fabrication, window opening reinforcement
08.07.21: Site preparation, foundation for the septic tank
14.07.21: pile foundation
20.07.21: septic tank and footings
23.07.21: surrounding work
29.07.21: garden work
30.07.21: container mock-up
02.08.21: STCC office pavilion inauguration with federal council Ignazio Cassis
17.08.21: inner structure off site fabrication
24.08.21: Inner Insulation, floor off site fabrication
02.09.21: Window installation
06.09.21: inner walls
09.09.21: Window installation
17.09.21: Container delivery and installation
>>> more photos of the installation and on site assembly process
>>> Final office pavilion photos
Location | Bangkok |
size | 30 sqm |
workplaces | 3-5 |
construction | Q3 2021 |